Long-idled US nuclear unit gets major approval to return 835 MW to grid

A long-shuttered US nuclear reactor has moved closer to a planned 2027 restart after securing two important regulatory boosts from federal agencies.
The US Federal Energy Regulatory Commission has approved Constellation’s request to transfer 760 MW of capacity interconnection rights from another Pennsylvania power plant to the former Three Mile Island unit 1.
The reactor, now called the Crane Clean Energy Center, is being prepared for a return to service in 2027.
Separately, the US Nuclear Regulatory Commission has issued for public comment its draft finding that restarting operations at the site would have no significant environmental impact.
Constellation announced in 2024 that it planned to restart the pressurized water reactor, which was shut down in 2019.
The company later filed an interconnection request with regional grid operator PJM to allow Crane to add 835 MW of emissions-free electricity to the grid.
The rights that could support return
To help support the 2027 restart schedule, Constellation filed a waiver request with FERC on March 31. The request sought permission to transfer capacity rights from Eddystone, a six-unit, dual-fuelled plant in Pennsylvania.
Two 380 MW units at Eddystone, known as Eddystone 3 and 4, had been scheduled to close last year.
However, they have remained online beyond their planned retirement date to support grid reliability under emergency orders issued by US Energy Secretary Chris Wright.
FERC has now granted the waiver, allowing Constellation to remove the Eddystone units from Capacity Resource status and make their capacity interconnection rights available for transfer. The decision was issued by FERC on June 1.
NRC opens restart review for public comment
The second regulatory boost came from the NRC. On June 8, the agency issued a draft environmental assessment and draft finding of no significant impact, or FONSI, for public comment.
The review evaluated the reasonably foreseeable environmental effects of allowing power operations to resume at Three Mile Island unit 1. At the time of its closure in 2019, the reactor had a renewed operating license valid until 2034.
Constellation has asked the NRC to approve one exemption request and three license amendment requests to support the resumption of power operations through the previous license expiration date.
The company has also said it plans to seek an extension that would allow Crane Clean Energy Center to operate beyond that, to 2054.
The NRC’s draft assessment concluded that restarting operations would not require a full environmental impact statement.
The Commission said in a Federal Register notice that “the NRC staff has made the preliminary determination that the proposed actions will not have a significant effect on the quality of the human environment. Therefore, the NRC staff has made the preliminary determination that it will not prepare an environmental impact statement (EIS) for the proposed actions and that a FONSI is warranted.”
The NRC will make its final decision after reviewing comments received during the 30-day public comment period, which runs until July 8.